Management of real estate, subsidiaries and stakes and shares of companies within the group of companies of Samruk-Kazyna JSC, which are in the investment period - design and construction

Subsidiary organization Samruk-Kazyna Development LLP

Documents

Samruk-Kazyna Development LLP is a subsidiary of Samruk-Kazyna Construction JSC

Samruk-Kazyna Development LLP was established on March 20, 2013 with the aim of implementing projects for the construction of real estate objects using "green" and eco-technologies with a high commercial component within the framework of the Law of the Republic of Kazakhstan "On Energy Saving and Energy Efficiency Improvement" and preparing for the ESCPO-2017 in Astana.

Since April 2019, Samruk-Kazyna Development LLP has been providing engineering services for technical supervision of facility construction and project management.

Due to the change in the composition of the participants of Samruk-Kazyna Development LLP, on 04.05.2023 re-registration was carried out. Participants: Samruk-Kazyna Construction JSC (100%).

Samruk-Kazyna Development LLP has the following accreditations and certificates of conformity:

- Accreditation certificate No. KZ91VWC00140480 for the right to manage projects in the field of architecture, urban planning and construction was received on January 20, 2023 for a period of 2 years.

- Certificate of accreditation No. KZ77VWC00148298 for the right to provide engineering services for technical supervision at technically and technologically complex facilities of the first level of responsibility was received on March 24, 2023 for a period of 2 years.

- ISO 9001-2016, ISO 45001-2019, directly applicable to the provision of engineering services for technical supervision at technically and technologically complex facilities (OKED codes: 71.12.1, 71.12.7), project management in the field of architecture, urban planning and construction (code OKED: 71.11.2) CERTIFICATE OF CONFORMITY No.KZ.7500831.07.03.02998 dated 14.04.2021 "Management of occupational safety and health protection" No.KZ.7500831.07.03.02997 dated April 14, 2021 "Quality management"

Completed projects:

1. LLP "SK Development" together with LLP "BI Corporation" implemented a project for the development of housing construction using "green" technologies "Green Quarter".

In 2018, the construction of the Green Quarter project was completed. The project consists of 10 residential blocks, 3 commercial blocks and a podium with an above-ground parking. The architectural concept of the Green Quarter project was developed by the British company AHR. The concept provides for the use of innovative green technologies - the buildings of the Green Quarter facility are certified for compliance with LEED (Leadership in Energy and Environmental Design) standards. The landscape design of the local area, a picturesque lake, a park with jogging and cycling paths, a fitness club, and a health center have been created on the territory. Head offices of Samruk-Kazyna JSC and most of its subsidiaries are located in T4 and T5 business centers.

2. Implementation of technical supervision of the construction of infrastructure facilities of the special economic zone "National Industrial Petrochemical Technopark" in the Atyrau region (sections Karabatan and Tengiz). External power supply

Customer: Karabatan Utility Solutions LLP

General contractor: ASPMK-519 LLP

Construction period: June 2019 - July 2019

Line length: VL 220 kV - 82 512.99 m., CL 110 kV - 420 m.

3. Implementation of technical supervision of the construction of an on-site highway of the special economic zone "National Industrial Petrochemical Technopark" in the Atyrau region (Karabatan section)

Customer: Karabatan Utility Solutions LLP

General contractor: RAD-Stroykomplekt LLP

Construction period: July 2018 - July 2019

Road length: 2.5 km.

Implementation of technical supervision of the construction of infrastructure facilities of the special economic zone "National Industrial Petrochemical Technopark" in the Atyrau region (sections Karabatan and Tengiz)

- Objects of engineering support of the GTPP. Engineering corridor. 1st turn;

- External water supply. 1st turn;

- Installation of water treatment and wastewater treatment. 1st turn.

Customer: Karabatan Utility Solutions LLP

General contractor: Bazis Construction LLP

Construction period: September 2019 - December 2021

4.Implementation of technical supervision at the facility "Medical center (polyclinic) with a hospital for 50 places of the production branch "Ozenmunaigas" in the city of Zhanaozen, Mangistau region"

Customer: Corporate fund "Company for the construction of facilities"

General contractor: SMK-Atameken LLP

Construction period: September 2021 - March 2022

Total area: 10 713 m2.

Implementation of technical supervision at the facility "MZhK "French Quarter" at the address of Atyrau, microdistrict. Avangard, the area of ​​the right bank of the river. Ural"

Customer: Stream energy company LLP

General contractor: BASTAU CONSTRUCTION LLP

Construction period: November 2020 - March 2022

Total area of ​​apartments: 32,000 m2.

5. Implementation of technical supervision over the construction of the facility "Multi-apartment residential complex on the Millennium Alley in Nur-Sultan, Almaty district, intersection of A. Baitursynuly, Zh.

Customer: BSK Stroy LLP

General contractor: Bazis Construction LLP

Construction period: March 2021 - August 2022

Total area - 115,981.3 m2

6. Implementation of technical supervision over the construction of multifunctional sports grounds in the Atyrau region

Customer: Corporate fund "Company for the construction of facilities"

General contractor: SMK - Atameken LLP

Construction period: June 2022 - November 2022

Number of sites: 4 units

Total area of ​​sports grounds: 25,200 m2

7. Implementation of technical supervision over the construction of the facility "Multi-apartment residential complex located at the address: Astana, Esil district, Uly-dala avenue, section 8/1, in the Expo area"


Customer: Smart Stroy-2050 LLP

General contractor: Consortium consisting of Smart Story-2050 LLP and EREN Group

Construction period: May 2022 - December 2022

Total area: 26,387.5 m2

8. Implementation of technical supervision over the construction of sports grounds in the village of Zhetybai, Karakiya district and in the city of Zhanaozen


Customer: Corporate fund "Company for the construction of facilities"

General contractor: SMK - Atameken LLP

Construction period: February 2023 - April 2023

Number of sites: 21 units

Total area of ​​sports grounds: 18,600 m2

Current projects:

1. Implementation of technical supervision over the construction of the facility "National Scientific Center for Infectious Diseases in the city of Almaty for 350 beds"


Customer: Corporate fund "Company for the construction of facilities"

General contractor: B&A Contractors SA LLP

Construction period: March 2021 - December 2023

Total area: 78,216.96 m2.

2. Implementation of technical supervision over the construction of the facility "National Coordination Center for Emergency Medicine in the city of Nur-Sultan for 200 beds"

Customer: Corporate fund "Company for the construction of facilities"

General contractor: MABCO Construction SA LLP

Construction period: March 2021 - September 2023

Total area: 54,745.8 m2.

3. Implementation of technical supervision over the construction of a sports and recreation complex in the village. Amankaragay, Auliekol district, Kostanay region


Customer: State Institution "Department of Architecture, Urban Planning and Construction of the Akimat of Auliekolsky District"

General contractor: AmirKazStroy LLP

Construction period: October 2022 - July 2023

Total area: 1,601.4 m2.

4. Implementation of technical supervision over the construction of a plant for the production of roofing and cladding materials in Astana

Customer: MetalFormer LLP

General contractor: ASTERA BUILD COMPANY LLP

Construction period: April 2023 - December 2023

Total area: 5,551.1 m2.

5. Implementation of technical supervision over the construction of a correctional office building for 150 places in the city of Kulsary, Zhylyu district


Customer: Corporate fund "Company for the construction of facilities"

General contractor: SMK - Atameken LLP

Construction period: February 2023 - October 2025

Total area: 722.2 m2.

6. Project management for the construction of the facility "Construction of a power plant based on a CCGT unit with a capacity of 1000 MW in the Turkestan region (Main site)"


Customer: PGU Turkestan LLP

General Contractor: Consortium of Doosan Enerbility Co. Ltd and Bazis Construction Limited Liability Partnership

Construction period: January 2023 - December 2025

Address: Astana, Nura district, 47a Kabanbay Batyr Avenue, BC "Alau Park", 2nd floor

Information center: +7 (7172) 277 860 (reception)

info@skdev.kz

www.skdev.kz

Chairman's Blog